Friday, September 17, 2010

#2 Green Renovation Continued

The shaping is done and has been approved by David Kidd and now we can start installing the drainage system, pea gravel layer and then the USGA Greensmix. The following pictures show you all the remaining steps besides the grassing. This coming Monday, we will start sodding the new green and this should take us approximately four to five days to complete.

In my opinion, the sodding is the most difficult task in a greens renovation. During the sodding process, the staff is very meticulous in placing the sod pieces so that the seems are smooth and consistent. A quality sod job ensures a quality putting surface.

Hearing bone drainage system.

Perforated drain pipe is laid into the trenches. Then a four inch layer of pea gravel is spread out over the entire area.

After the pea gravel is installed, we check the final grade and make any adjustments necessary.

Then the sand installation begins. Twelve inches of USGA Greensmix is installed.

Once all of the greensmix is installed, we take a lot of time compacting the sand so that settling will not occur in the future. In order to compact the sand we use the mini-ex, plate compactor and a lot of water to make sure not only are the depths accurate but to ensure the stability of the sand. This process will take several days. In comparison to time, the installation of the drainage ditches, pipe, pea gravel and sand only took two and half days.




See you when we are sodding.












No comments:

Post a Comment